IMAGE GALLERY:
Madrid Complex | Madrid Construction Site

January 22, 2003
(Click for hi-res image)
Steel Erection
Now that the weather is cooperating a little better in Madrid, the welds on the main reflector structure are being painted.
This painting was originally scheduled to occur prior to the main reflector lift but was delayed due to rain. The painting must
be completed prior to the start of panel installation.