IMAGE GALLERY:
Madrid Complex | Madrid Construction Site

March 5, 2003
(Click for hi-res image)
Steel Erection
The major steel erection activities have now been concluded with the installation of the last main reflector panel. The only
additional erection activities remaining are the installation of the M5, M6, and M7 mirrors and the pedestal shroud.